We are in the process of converting many of our standard calendars to extended calendars. We are having issues with three of our calendars that calculate correctly but skip a few months. One is to calculate two business day before the last business day of the month. It calculates all correctly except Nov 2020, January 2022, and October of 2022, where it schedules that day on the weekend. This is the same for the other calendars we are trying to create. We have the condition set to WORKD#L with an Adjustment of -2, not to schedule on holidays, with the standard holiday calendar attached. The Non-workday action doesn't seem to matter as whatever is selected, it does not calculate correctly. Need help with this. Is this a bug?
Release : 11.3.6
Component : CA Workload Automation AE (AutoSys)
Use WORKDM02 as the condition key word and 0 for the adjustment.
Reference the following document:
WORKDMnn Specifies that the schedule that is generated by the extended calendar includes the nnth workday of the month, counting backwards.
URL:
https://techdocs.broadcom.com/us/en/ca-enterprise-software/intelligent-automation/workload-automation-ae-and-workload-control-center/11-3-6-SP8/scheduling/ae-scheduling/manage-your-calendars/date-condition-keywords.html