It appears the project name is appearing under every task in the timesheet.
Is there a way to remove it as it takes up space?
Release : 15.8.1
Component : CA PPM SAAS APPLICATION
The indicator below the task is not the project name, but that of the summary task.
The parent summary task can be seen in the Clarity Gantt or MSP.
The only way to remove the summary task from the MUX:
1. Deleting the summary task or
2. Outdenting these non summary tasks to where they are no longer under the summary tasks. This can be done in the Clarity Gantt or in MSP