Rally Planned & Actual Dates Impact on Clarity Task Sync
search cancel

Rally Planned & Actual Dates Impact on Clarity Task Sync

book

Article ID: 200939

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Does the Rally Sync check Rally Planned Start / Finish (End) Dates or Actual Start / Finish (End) Dates from Rally when syncing with Clarity tasks? 

Environment

Release : All

Component : CA PPM SAAS RALLY

Resolution

Both planned and actual dates are checked by the sync, see Examples for Populating Task Dates in Classic PPM in TechDocs for more information.