When trying to populate a cost plan via Project > Financial Plans > Action > Populate from Investment Team
the following error appears: REVMGR-01019: Current Exchange Rate does not exists.
Release : 15.8
Component : CA PPM SAAS APPLICATION
1. Check the Project > Settings > Rate Source and Cost Source Rate Matrices.
Check what the Exchange Rate Type is set to and make sure there is a matching foreign exchange rate effective date.
2. Check Administration > Finance > Setup > Foreign Exchange Rates
Filter for the currency, exchange rate type to check the Effective Date