Schedule Dashboard - What are the Thresholds and can they be changed?
search cancel

Schedule Dashboard - What are the Thresholds and can they be changed?

book

Article ID: 200337

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

How do I find out what the current red, yellow, green thresholds are for the schedule indicator on this Schedule Dashboard portlet? Also is it possible to change it for fields such as Overall Status and Schedule %?

Environment

Release : All Supported Releases

Component : CA PPM SAAS STUDIO

Resolution

You can view and change the thresholds by going to the Attributes for the portlet's the related query

  1. Go to Administration -> Queries and search for 'Schedule Dashboard'. Click to open
  2. Click on the Attributes Tab
  3. Find 'Schedule %' and click to open
  4. Edit the From and To values as needed 
  5. You can also change the descriptions accordingly
  6. Save and Return
  7. Repeat steps for all other applicable attributes you want to change. 

For more information on the thresholds for the attributes for this portlet, see Schedule Dashboard Portlet