According to this documentation: https://techdocs.broadcom.com/us/en/ca-enterprise-software/business-management/clarity-project-and-portfolio-management-ppm-on-premise/15-8-1/Using-Classic-Clarity-PPM/project-management/project-schedules-in-the-gantt-view/manage-project-task-dependencies-and-relationships.html
Specifically here: "The dependent task is displayed before or after the task based on whether it is a predecessor or successor task."
In the Gantt view, the tasks should display in order, with predecessors displaying before a successor. In 15.7.1 this isn't working. For example:
Notice, that even though "Task 1" is a successor to "Project2_task1" it displays first.
Release : 15.7.1
Component : CA PPM APPLICATION
This issue is resolved while using the latest version of Clarity, 15.8.1.