Team task assignment not generating in timesheet

book

Article ID: 199622

calendar_today

Updated On:

Products

Clarity PPM On Premise

Issue/Introduction

We are assigning a Team to the Effort task with resources ( open for time entry).  When accessing the timesheet, the resources on the team cannot view and select the effort task that they were assigned to.  Tested with other tasks and the same result, we may be missing a setting for team task assignment to populate in timesheet.

Environment

Release : 15.8.1

Component : CA PPM FINANCIAL MANAGEMENT

Resolution

In Classic need to make sure team is Open for Time Entry and Track Mode is set to PPM, this is not something you can do in New UX.