Issue/Introduction
- Direct reports / expected resources are not listed under the Timesheet Review & Approve tab in the New User Experience (UX)
- What are the access rights needed to see users on this tab?
Environment
Release : All Supported Releases
Resolution
Step 1: Grant the user Resource - Approve Time rights to the required resources
- To grant this access at the instance level in Clarity:
- In Classic Clarity, go to Administration -> Resources
- Click on the resource who requires the access
- Click on the Resource's Access Rights tab and select 'Instance' from the drop down
- Click Add
- Select the 'Resource' object and click Next
- Click the check box next to 'Resource - Approve Time' and click Add and Continue
- Click the check box next to the Resources the user should have access to and click Add (or click 'Add and Select More' to add additional resources)
- Have the user log out of Clarity and Log back in for the rights to refresh
Step 2: If that doesn't help, also check to make sure that the needed resources are Open for Time Entry with Track mode of PPM in Home->Resources