Which Time Slices are used by the Resource Planning portlets, specifically the Monthly/Annual periods for the Workloads portlet?
Release : 15.8.1
Component : CA PPM
These portlets do use the insta slices which are internal slices that are not visible on the User Interface.
Both Monthly and Annual periods use the monthly internal slices.
For example:
Slice ID: 111 - Monthly Allocation
Slice ID: 114 - Monthly Actuals
Slice ID: 110 - Monthly Availability