STEPS TO REPRODUCE:

  1. Go to Clarity - Open a project - go to Financial Plans
  2. Pick an existing plan with at least two lines and some data
  3. Now click on Configure and add Last Updated Date and Updated by to the list
  4. Note the time/user on it (ideally something that's been created with another user not today)
  5. (If needed connect with another user), update the plan by changing any value in one row
  6. Save

 

Expected Results: Only the updated row should have a new value for Last Updated Date and Updated by

Actual Results: All rows in the Cost plan detail will be updated with the same information for Last Updated Date and Updated by even though they were not updated at this time with this user

Environment

Release : 15.6.0 - 15.9.2

Component : CA PPM FINANCIAL MANAGEMENT

Resolution

This is logged as DE57439, fixed in 15.9.3