Issue/Introduction

Steps to Recreate

Prereqs-

Have a Project with resources assigned to tasks with rates assigned

  1. Go to Project>Financial Plans
  2. Create a Cost Plan
  3. In the Cost plan Action Menu select 'Populate from Task Assignments'

Expected Result - Planned Cost would match the assignments

Actual Results - Planned Cost is showing zero

Environment

Release : 15.8

Component : CA PPM SAAS APPLICATION

Resolution

Resolved in 15.8.1