Issue/Introduction

When Project Manager, or anyone, clicks on Project - Preview Content then an error pop-up's showing:

 

Cause

In New UI, Project Managers require Global Access Rights to Create and Edit Status Reports

Environment

All

Resolution

Provide the following Global Access Rights to the user:

1. Status Report - Edit All

2. Status Report - View All

3. Project - Edit All

4. Project - View All