When doing a Replace on the Task tab, Assignment view occasionally you will get the following error: "ERROR: Action is not supported for Milestone or Summary Tasks"
Steps to Reproduce:
Expected Result: The new resource to be on the assignment
Actual Result: You may get " ERROR: Action is not supported for Milestone or Summary Tasks"
Caused by CLRT-72307
Our sustaining team reviewed this issue. There are no current plans to make any changes to this area of the product.
Make the replacement via the Task Properties page.
Reference CA PPM Customer Defect Resolution Policy