In Harvest workbench, for a particular project we have 7 stages,
1.Dev
2.Obselete
3.Test
4.Qual
5.Staging
6.Prod
7.Snapshot
Here in Dev, I have added a new UDP process to promote packages to one of the Qual servers. When I try that option, the package got migrated to that particular server and we can see the new code reflecting on the server.But the package has been moved to Obselete state instead of Qual state in the tool. Do we have any options or settings to set the option "promote to Qual" as default (Instead of going into Obselete state)? I have even try to change the order of states in properties, but still the package is getting into Obselete state. Please advise.
CA Harvest SCM all versions and platforms
In Administrator Tool, navigate to your project, state and promote process and open the properties window for that promote process:
In the “Promote To” field make sure the correct state is listed there: