Clarity PPM: Program Does not show Cost Information

book

Article ID: 197391

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

How does program functionality work with roll-up of sub-project financials, i.e. budgeted cost, actual cost, etc?

There are sub-projects with budget plans, but the data is not rolling up to the program. 




Environment

Release : 15.8.1

Component : CA PPM SAAS APPLICATION

Resolution

Programs cannot have their own team therefore, no allocations or ETC will be available.
The Program cost plans are not expected to roll-up the actuals from the sub-projects that are associated with the program.

As an alternative to program cost plans, we advise to use the hierarchy tab.



Additional Information

https://techdocs.broadcom.com/content/broadcom/techdocs/us/en/ca-enterprise-software/business-management/clarity-project-and-portfolio-management-ppm-on-premise/15-8-1/Using-Classic-Clarity-PPM/project-management/group-projects-and-investments-under-a-parent-program.html#concept.dita_1d14d7dcded3e2e1facf7d6ddba392b73b0963ec_CreateaProgram