Project Actuals and ETC Show Zero in Project task in New UX

book

Article ID: 197038

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

Project actuals and ETC shows in Zero or FTE format in Project taks in new ux. 

Environment

Release : 15.8

Component : CA PPM SAAS APPLICATION

Resolution

Project Task page in new UX derive data from the General setting from user account, So if FTE is selected it will show as 0 or 0.6 or 1 in the actuals in task of the project . Change the general page setting to hours , post which it shows the correct data. 

Attachments