Following an IPL, the CA Jobtrac VINIT started task is being started twice.
First time VINIT is being started starting with parameter "PARM=INIT"
Second time VINIT is started once more with "PARM='ONLY=GJTRVMXT'".
Release : 11.0
Component : JOBTRAC
S VINITx,PARM='ONLY=GJTRVMXT' is usually only issued when the AMR table did not activate successfully on the first start of JOBTRAC
So, only 1 start of VINIT is required .. The first startup of VINIT will show that the status of AMR