I am unable to edit team allocation data in some projects through OWB. Why?

book

Article ID: 196338

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

In OWB I am unable to edit team members allocation data on the TSV fields.

I can change the cell value, but as soon as I come out of the cell, the value reverts back to its original value.

The issue is project specific. There are some where I can edit and save the changes and some other projects where I can not.

Cause

This was analyzed by engineering through CLRT-47502

Environment

Any Clarity PPM / OWB release.

Resolution

This only happens on master / subproject structures.

By design you are not allow to edit team data if subprojects exist.

We disallow the editing of Team/Project specific data in Master subs because we have no way of knowing which Team record the user wants to update.

Perform the changes in Clarity instead when subprojects are involved