In Classic PPM the 'Is Late' field depends on specific criteria
search cancel

In Classic PPM the 'Is Late' field depends on specific criteria

book

Article ID: 196230

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

The Classic UI has a field called "Is Late", in the Tasks module as shown in the screenshot below. How is the colour of this field determined?

Environment

All supported clarity releases

Resolution

The "Is Late" field always relies on the Baseline. This field will not be accurate if there are no Baselines defined.

It is set to Green if the Task Finish Date is equal to or less than the Baseline Finish Date.
It is set to Red if the Task Finish Date is greater than the Baseline Finish Date.

It is not dependent on the Task Status either.