Classic UI - What are the dependencies for the 'Is Late" field in Tasks?

book

Article ID: 196230

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

Product: Clarity PPM
Keywords: Is Late; Tasks; Projects

The Classic UI has a field called "Is Late", in the Tasks module as shown in the screenshot below. How is the colour of this field determined?

Environment

Version: 15.8.1

Resolution

The "Is Late" field always relies on the Baseline. This filed will not be accurate if there are no Baselines defined.

It is set to Green if the Task Finish Date is equal to or less than the Baseline Finish Date.
It is set to Red if the Task Finish Date is greater than the Baseline Finish Date.

It is not dependent on the Task Status either.