Project - View access type needed with Resource Hard booking access
search cancel

Project - View access type needed with Resource Hard booking access

book

Article ID: 196204

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

It looks like Project - View and Project - View management Access are working as same when the user has Resource - Hard book access to a user.

The description of the access right Resource - Hard Book - All in Clarity states:

"Allows user to Soft or Hard book all resources to an investment that the user has been granted view management rights."

Based on that description should both Project - View and Project - View Management allow the user to update the team on a project?

Environment

Release : All Supported Releases

Resolution

Both Project View rights will give the user access if they have Resource - Hard Book or Resource Manager (auto) access to the user:

  • Project View - Management - Can be granted at Global, OBS, or Instance level
  • Project - View - Can be granted at a OBS or Instance level

The description only mentions  Project - View Management as it's the one access right available at the global level (Project View is not).