Extend Finish Period of Project Cost Plan

book

Article ID: 195780

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

We would like to extend the finish period of a project to 2025. Unfortunately the selection list only goes up to December 2023. How would we go about extending the selection list to December 2025?

Environment

Clarity Application

Resolution

The Clarity Fiscal Time Periods need to be created.

1) They are set as an administrator at Click on Administration > Finance > Setup > Select Entities > Edit your entity > Fiscal Time Periods tab

2) There you can setup the Fiscal Time Period to suit your business needs.

3) Select the created fiscal time periods and go to the top right-hand side of the page, click Action > Activate.

 

Additional Information

Create Fiscal Time Periods

Attachments