Steps to Reproduce:
1. View a project in Modern UX
2. Select the TASKS module
3. Select the GRID view
4. Right-click a task, then select INSERT ROW BELOW
5. Type the Task Name, then click Enter
Expected Result:
The new task is inserted below the task that was right-clicked on.
Actual Result:
(After refreshing the grid) the new task is show according to the column being sorted on. If for example, "WBS Sort" is used, the task goes to the bottom of the list.
Release : 15.8
Component : CA PPM SAAS APPLICATION
The feature (Insert Row Below) works like an Excel spreadsheet works. It is possible to add a row right below the selected row, but after sorting it, it is impossible to have the same order again.
It is working as expected.