Access Rights Needed to Edit Default Allocation
search cancel

Access Rights Needed to Edit Default Allocation

book

Article ID: 193941

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

What access rights are needed to edit the default allocation percentage of a project team member for a project that the user is not the project manager of?

The user has 'Project - Edit Management' instance rights over the project, as well as the 'Resource - Soft Book - All' right, but still is not able to edit the allocations.

Environment

Release : All Releases

Component : CA PPM Resource Management

Resolution

This depends on what the Booking Status of the team record is, if the Booking Status is Hard, the user will need 'Resource - Hard Book' rights over the resources. 

Having the 'Resource - Soft Book' right would only grant the user access to update the allocations on soft booked team members on this project.