We have received a request that submitted budget cost should not be updated until it gets approved or rejected. The allocations never change in the submitted budget, however, the actuals are getting updated.
We know that 'Import Financial Actuals' job makes the update.
Please let us know if we can keep the submitted budget remains unchanged until it gets approved or rejected.
Release : All Supported Clarity releases
Component : CA PPM SAAS FINANCIAL MANAGEMENT
Open. All transactions that are entered against the project can be fully processed. Select this status to enable the project for financial processing.
Hold. No new transactions can accumulate on the project.
Closed. No new transactions can accumulate on the project. When you mark the financial status as "Closed", it is no longer open for financial processing.