Description:
After we upgraded from Clarity v12.x to v13.x, our Budgeted Cost Values are wiped out or changed to an unexpected value.
We reviewed the information on page 25 of the CA Clarity PPM v13.0.00 Change Impact and Upgrade Guide, regarding changes in the 'Simple Budget' page for the removal of the 'Forecast' attributes and the upgrade actions recommended.
The following Simple Budget forecast fields were removed:
The following fields were renamed:
See the Financial Management User Guide for more information.
The Simple Budget page will be refreshed during the upgrade if it was not customized.
Upgrade action:
However, this does not explain why our data changed after the upgrade.
Can you please explain what happened?
How can we prepare for our production upgrade to avoid this problem?
Release: ESPCLA99000-13.2-Clarity-Extended Support Plus
Component:
Solution:
If 'Forecast Equals Budget' (attribute ID = 'IS_FCST_EQ_BDGT') is CHECKED, in v12, in the Simple Budget page, the value in the 'Budgeted Cost' attribute is copied into the 'Forecasted Cost' attribute and is not open for editing. If the 'Forecast Equals Budget' attribute is UNCHECKED, the 'Forecasted Cost' attribute is open for editing to enter a different value than the 'Budgeted Cost'.
After the upgrade to v13, the same attribute ID 'IS_FCST_EQ_BDGT' now has a new label and new functionality. The new label is 'Budget Equal Planned'.
Now, the 'Planned Cost' attribute value is copied into the 'Budgeted Cost' attribute and is not open for editing. If the 'Budget Equals Planned' attribute is UNCHECKED, the 'Budgeted Cost' attribute is open for editing to enter a different value than the 'Planned Cost'.
Due to the changes in v13, some customers may want to take the following upgrade actions:
Example 1:
In v12, you may have Planned Cost = $15,000, Forecasted Cost = $14,000, Budgeted Cost = $14,000, Forecast Equal Budget = CHECKED
If this attribute remains CHECKED, after the upgrade, the 'Forecasted Cost' attribute is removed and the value in the 'Budgeted Cost' attribute is updated with the value that is in the 'Planned Cost' attribute. Therefore, after the upgrade, Planned Cost = $15,000, Forecasted Cost attribute is removed, Budgeted Cost = $15,000, Budget Equal Planned = CHECKED
Example 2:
In v12, you may have Planned Cost = $15,000, Forecasted Cost = $14,000, Budgeted Cost = $14,000, Forecast Equal Budget = CHECKED
Before the upgrade, in v12, if you change the 'Forecast Equal Budget' = UNCHECKED, after the upgrade, the 'Planned Cost = $15,000, Forecasted Cost attribute is removed, Budgeted Cost = $14,000, Budget Equal Planned = UNCHECKED
Keywords: CLARITYKB, changeimpact.