MSP Lightweight - what type of data is exported versus bidirectional?
search cancel

MSP Lightweight - what type of data is exported versus bidirectional?

book

Article ID: 192412

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

What are the differences between lightweight and bidirectional in MSP (Microsoft Project) schedule formats?

Environment

Release : 15.7.1

Component : CA PPM MICROSOFT PROJECT (MSP)

Resolution

Per the documentation, the lightweight integration lets you pass data only to the following attributes 

  • Task Name
  • Start
  • Finish
  • % Complete
  • Predecessor
  • Successor
  • Milestone (flag)
 

Additional Information

Lightweight Integration (BETA)

  • Clarity PPM and MSP integration known defects - Support Technical Document Index (KB: 15956)

  • Clarity PPM and MSP integration - List of knowledge documents (KB: 71385)

  • See KB: 141061 for tips on how to optimize use of Self Service for Clarity PPM