Clarity PPM - Project Progress field is not updating to Started
book
Article ID: 192151
calendar_today
Updated On:
Products
Clarity PPM SaaS
Clarity PPM On Premise
Issue/Introduction
The "Progress" field on my Project hasn't changed status, should it automatically change?
Environment
Release : 15.7.1
Component : CA PPM SAAS APPLICATION
Resolution
This is functioning as expected. The field must be manually adjusted, the Progress will not update automatically.