When a resource is added to a project under Team tab, in the list view it shows Project Start and End dates by default. However, when I open the properties page, it show blank value for Start and End Date. Is it by design so users have to enter Start and End dates on the properties page?
Release : All Supported Releases
Component : CA PPM SAAS APPLICATION
This is by design. If the team member's start/finish dates haven't been manually populated, these will show as blank on the team member's properties page. The "Blank" option allows the option for those who want the user's start/finish date to automatically update based on changes to the investment start/finish date to ensure the resource is allocated the entire duration of the project.
To have dates automatically populate when a team member is added you can set a default for the date fields on the team object
Example with Start date field: