We've modified the configuration in Production and now have 3 logstash processes running, each is still maxing out at 50k metrics and then crashes. We were at around 70/80k metrics before with one process, how can we have 150k processes?
Environment
Release : 10.7.0
Component : APM Agents
Cause
Server hitting capacity limits
Resolution
Changed logstash metric clamp from 80K to 50K and added error logging. No recurrence in 17 days.