If a project has a task that depends on another project, update the task in Microsoft Project (MSP), and save it back to Clarity, all tasks, except the dependent task, of the project that has the dependent task will be removed in Clarity.
STEPS TO REPRODUCE:
EXPECTED RESULT: The change of the "Task_s01" is saved and the other tasks of the Project B that are not opened in MSP exist without a change.
ACTUAL RESULT: The other tasks of the Project B will be removed.
Release : 15.6.1
Component : CA PPM SAAS APPLICATION
It works by design.
In order to avoid the behavior, we need to specify the project with the dependent task as a sub project to the project that the external dependency is linked to. e.g. Project B has to be a sub project of the Project A.