Clarity PPM: Tasks are removed after updating a task in MSP.
search cancel

Clarity PPM: Tasks are removed after updating a task in MSP.

book

Article ID: 191813

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

If a project has a task that depends on another project, update the task in Microsoft Project (MSP), and save it back to Clarity, all tasks, except the dependent task, of the project that has the dependent task will be removed in Clarity.   

STEPS TO REPRODUCE:

  1. Create the following Projects and tasks.

    Project A
    Task01 & Task02
     
    Project B
    Task_s01 & Task_s02
    Task_s01 has dependency to the Project A 
     
    Both Projects Scheduler is set to "Microsoft Project Bidirectional".

  2. Open the Project A in MSP by selecting "Microsoft Project Read-Write" from 'Open Scheduler' drop down list in Clarity.
    --->
    All tasks from the Project A and "Task_s01" from the Project B are displayed in MSP.

  3. Modify Start Date of the "Task_s01" and save it back to Clarity.

  4. Open the Project B > Tasks in PPM.

EXPECTED RESULT: The change of the "Task_s01" is saved and the other tasks of the Project B that are not opened in MSP exist without a change.
ACTUAL RESULT: The other tasks of the Project B will be removed.

Environment

Release : 15.6.1

Component : CA PPM SAAS APPLICATION

Resolution

It works by design.

In order to avoid the behavior, we need to specify the project with the dependent task as a sub project to the project that the external dependency is linked to. e.g. Project B has to be a sub project of the Project A.

Additional Information

125731: Clarity PPM MSP Interface opens up Projects with dependent tasks

(Community) External Dependency Issue with MS Project Integration