Issue/Introduction

Unexpected behavior in Clarity new UX when building a cost plan manually charge codes cannot be selected. Try to associate large number of charge codes at the project level, e.g. one can XOG charge codes in bulk. Notice that charge codes cannot be selected in the new UX (unlike classic PPM).

 

 

Environment

Clarity PPM 15.7.1

 

Cause

This is working as designed and a matter of getting used to the new PPM modern UX.

Resolution

The charge codes updated via XOG just needs more value so as to make it a discriminant identifier, just entering characters may not always help filter the required charge code from a list of over 100s of charge codes.