Top Secret CPF ON but INACTIVE between nodes
search cancel

Top Secret CPF ON but INACTIVE between nodes

book

Article ID: 190643

calendar_today

Updated On:

Products

Top Secret

Issue/Introduction

CPF show ON but is inactive between our production node and our test node.  Discovered the CCI task was stopped on  test system
issued the TSS CPF(REFRESH), the command completed successfully but the nodes still show inactive. 

Environment

Release : 16.0

Component : CA Top Secret for z/OS

Resolution

TSS MODIFY(CPFNODE(nodename=START))
TSS MODIFY(CPF(REFRESH))

issue ENF DISPLAY,LINK.

This command shows the status of any CCI links to verify the
CCI connection status is ACTIVE.