In an Idea in Classic Clarity, a user changes the Start Date and Finish Date forward one month. After saving, either the Start Date or Finish Date reverts back to its original Date. This issue is reproducible from both the Idea list view and Idea properties page.
STEPS TO REPRODUCE:
Expected Results: The new dates will be saved
Actual Results: The Start or Finish date will revert back to the original date.
Note: If you have one or no resources on the Team, the issue does NOT happen.
Release : 15.4.1 and higher
Component : Clarity Project Management
This issue was reviewed and determined it would not be fixed. Users can use one of the workaround options below.