Issue/Introduction
Why COST_BUDGET_EQUIP, COST_BUDGET_EXPENSE and COST_BUDGET_MATL columns of NBI_PROJECT_CURRENT_FACTS table are NOT updated with Budget plan's planned cost amount?
Environment
Release : 15.6
Component : CA PPM FINANCIAL MANAGEMENT
Cause
Due to a database schema change these fields are no longer populated.
Resolution
Will need to use Data Warehouse tables or other tables to get the data.