Issue/Introduction
We would like to see the Projects tasks in structured format as we defined in Classic Clarity PPM UI.
But, the Parent--> Child relationship is not appearing in New User Experience (UX).
Environment
Release : 15.7 (Beta), 15.7.1 and higher
Component : CA PPM SAAS PROJECT MANAGEMENT
Resolution
You can use the timeline view in the Tasks section of the project in the New UX which shows parent/child task relationships.
To get to the Timeline view:
Click on a project in the New UX
Click on the Tasks tab
Click on the Timeline icon on the right hand side (Highlighted in yellow below)
Additional Information
For more information on the Timeline view see
Managing Tasks in the Timeline Layout
See KB:
141061
for tips on how to optimize use of Self Service for Clarity PPM