Issue/Introduction
Is there a way to clear pending actuals without going through timesheets for a resource that is inactive/no longer working with the company?
Environment
Release : All Supported Releases
Component : CA PPM SAAS APPLICATION
Resolution
If the pending actuals were created via a timesheet, the only way to delete the pending actuals would be through the timesheet:
Go to the user's timesheet
Return the timesheet
Delete the task(s) or remove all time on the task
Save the timesheet (The Timesheet doesn't have to be resubmitted)