There is a column 'Assigned Resources' added to the Task Gantt.
Is there any way to add it to the task view - list filter/columns ?
Environment
Clarity PPM 15.x
Resolution
The Assigned Resources field is not an available field to be added to the Task List nor Task filter views. It is specific for the Scheduler/Gantt views.