Assigned Resources in Task List view
search cancel

Assigned Resources in Task List view

book

Article ID: 187582

calendar_today

Updated On:

Products

Clarity PPM On Premise Clarity PPM SaaS

Issue/Introduction

There is a column 'Assigned Resources' added to the Task Gantt. 

Is there any way to add it to the task view - list filter/columns ?

 

 

Environment

Clarity PPM 15.x

Resolution

The Assigned Resources field is not an available field to be added to the Task List nor Task filter views.
It is specific for the Scheduler/Gantt views.