ERROR "INV-0023: Missing Budget Benefit Start or Budget Benefit Finish date" in New UX

book

Article ID: 187096

calendar_today

Updated On:

Products

Clarity PPM SaaS Clarity PPM On Premise

Issue/Introduction

Unable to save the budgeted Start of Finish Date in the Modern User Experience (UX)

  1. Log in to New UX
  2. Go to Blueprint and add Budgeted benefit Start and Finish date in any Blueprint Layout
  3. Go to Classic and attach some projects to blueprint
  4. Open Project in New UX
  5. Go to detail Page and try to fill budgeted start of finish date

Expected result : User should able to save the budgeted start or finish date
Actual Result :- INV-0023: Missing Budget Benefit Start or Budget Benefit Finish date

Cause

 Budgeted benefit Start and finish date are  conditional fields. When we fill one of the budget benefit start date system is checking for finish date and giving error since there is no save button in New UX this can't be filled. Date filled in either of the fields will get wiped off by system as it do not find both the dates on same time. 

Environment

Release : 15.8

Component : CA PPM SAAS APPLICATION

Resolution

Fixed in 15.8.1 as DE54025