New tasks created in Clarity PPM are exporting to Microsoft Project (MSP) as Fixed units instead of Fixed work
- The MSP project setting is correctly set as Default task type of Fixed Work (both for the project exported, and also all new projects in MSP)
Steps to Reproduce:
- Create a new project in PPM
- Assign one or more team members to the project
- Go to the project Gantt in Classic Clarity PPM
- Create a new task in PPM (Non Fixed Duration)
- Assign a resource to the task with some ETC
- Export the project to MSP
- Add Type column to the task view and view the Type value for the task
Expected Results: Type value is Fixed Work since the default task type for the project is set to Fixed Work
Actual Results: Type value is Fixed Units