If we update a PMO Add-in Portlet Query, will an upgrade overwrite it?
book
Article ID: 186551
calendar_today
Updated On:
Products
Clarity PPM SaaS
Clarity PPM On Premise
Issue/Introduction
If we update a query used by a PMO add-in Portlet, will it get overwritten every time we upgrade?
Environment
Release : All supported Releases
Component : CA PPM SAAS APPLICATION
Resolution
- There will be a risk a PMO Upgrade will overwrite it.
- It's recommended to either create a new portlet and modify that one, or save the query updates locally and add them back in post upgrade.
- Here's what the documentation mentions for these types of customizations at Install or Update Content Add-ins:
If your environment was customized before installing or updating an add-in, note the following points:
-
When you apply an add-in, the customization of objects such as portlets and pages in Studio can be overwritten. Your user interface changes.
-
You cannot uninstall an add-in.
- To avoid overwriting any Studio customizations, consider what the add-in is going to change before installing or applying it.