Issue/Introduction

Can I have more than 15 charts in my Table per Item with Multiple Metrics On Demand report?

I have added 15 components and receive a warning that 15 is the limit when I attempt to add more:

The number of select entries exceeded the number of allowable choices: (15)

When the error is expanded:

You may only select 15 items in this grid.

I need to add more than 15 components to the report.

Environment

Release: All supported Performance Management releases

Component: IM Reporting / Admin / Configuration

Resolution

Put the components in a group and select the group as the context when configuring the report.

For "Metric Calculate Level", select "Component"