Data Discrepancy between Timesheets and Capacity Report
search cancel

Data Discrepancy between Timesheets and Capacity Report

book

Article ID: 186256

calendar_today

Updated On:

Products

Clarity PPM SaaS

Issue/Introduction

A project shows more hours on the Clarity Team page and the Capacity reports as well. However, the timesheets for this project reflect fewer hours. 

What could be causing this discrepancy?

Environment

Release : Any

Component : CA PPM APPLICATION

Resolution

The additional actual hours can be coming from extra transactions that were manually created or xogged in. These transactions can be found by querying the PPA_WIP table or checking in the UI under various transaction related pages such as: Posted Transaction Review, Transaction List and the Create WIP Adjustment pages.