Issue/Introduction
We have few time slices with number of periods defined as zero. Will this have any impact on performing the Clarity upgrade?
Environment
Release : All Clarity releases
Component :
Resolution
There should be no issue with you leaving those slices set to 0. Before you run the upgrade, we recommend to pause all jobs and to ensure nothing is running.