Issue/Introduction

When trying to configure the Project Schedule Gantt the attribute 
PROGRESS PERCENT ATTRIBUTE
does not have any values to select.

STEPS TO REPRODUCE: 

 1. Go to the Project Dashboard tab from the Home page.
    - Note this is a PMO tab and page.
 2. Configure the Schedule Dashboard -add it or restore defaults if it is not showing.
 3. In List Column Section go to Fields
 4. On Gantt Schedule [virtual] open the properties
 5. Under Primary Bar select item in Progress Percent Attribute

Note the same behavior can be seen on the Program Dashboard.

One work around is to configure the attribute on the Project List Page Gantt Schedule field.

Cause

This has been reported as defect DE53638

Environment

Release : 15.7.1

 

Resolution

This has been reported as defect DE53638 and is currently under review.