When creating requisitions, sometimes the start and finish dates are blank at the requisition properties.

book

Article ID: 17116

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction



When creating requisitions, sometimes the start and finish dates are blank at the requisition properties.
What does influence the requisition to be created with or without dates?

Environment

Any PPM release

Resolution

The date population on the requisition is controlled by the team member allocation.
If the Default allocation % is zero and there is no segment with non zero allocation at team level, then the requisition is created with blank dates.
PPM assumes that if the team member does not have any allocation, the requisition will not have any allocation to replace to and therefore dates are blank.
When creating requisitions, please ensure that the team member does have some allocation.