Audit trails on Project object attributes: 'Actuals Sum for Labor Resources' and 'ETC' not available in CA PPM from 14.x and later versions

book

Article ID: 16846

calendar_today

Updated On:

Products

CLARITY PPM FOR ITG CLARITY PPM FEDERAL Clarity PPM SaaS - Application Clarity PPM On Premise

Issue/Introduction

After upgrading CA PPM from 13.2 to 14.x and beyond we are no longer able to create Audit trails on Project object attributes: 'Actuals Sum for Labor Resources' and 'ETC'.

Can you confirm the functionality has been altered or removed?



After upgrading CA PPM from 13.2 to 14.x and beyond we are no longer able to create Audit trails on Project object attributes: 'Actuals Sum for Labor Resources' and 'ETC'.

Can you confirm the functionality has been altered or removed?

Environment

Windows, Linux

Resolution

The attributes 'Actuals Sum for Labor Resources' and 'ETC' are now virtual attributes. The changes occurred from CA PPM version 14.1

By design virtual attributes cannot have an audit trail configuration. The behavior is expected.