Milestone Count Discrepancy
search cancel

Milestone Count Discrepancy

book

Article ID: 16513

calendar_today

Updated On:

Products

CA Agile Central On Premise (Rally) CA Agile Central SaaS (Rally)

Issue/Introduction



When viewing Charts on a Milestone, the count of work items does not match the count shown in the Scheduled tab.

 

<Please see attached file for image>

Picture1.png

 

Furthermore, the number of items listed in the Scheduled tab does not match the count shown as an icon on the Scheduled tab.

 

<Please see attached file for image>

Picture2.png

Why is there such a discrepancy with the item counts under a Milestone?

 

 

Environment

Release:
Component: ACSAAS

Resolution

The items showing in the Milestone Burnup Chart and the Cumulative Flow Charts include all work items that roll up to the Milestone. 

 

The count shown by the Scheduled tab icon represents only work items directly associated to the Milestone.

 

The list of items displayed in the Scheduled tab will show any item that is directly associated to the Milestone and its children, with no regard to whether the children are directly associated.

 

Please see the Help article for more: Create and Manage Milestones 

 

The below video on this difference, which should add some clarity:

 

 

 

Additional Information

Related articles:

What is the difference between the Planned Count and Accepted Count on a Milestone Burnup Chart?