How is Effort Spent calculated in the new User Experience?
Effort Spent is calculated as Project Actuals / (Project Actuals + ETC) x 100.
Additionally, the Investment Allocation job to ensure that effort spent gets updated.
To run the Investment Allocation job:
Reference New User Experience: Measure Trends and Publish Project Status Reports for further information on Status Reports in the New User Experience.