Looking for a Timesheet Approval process with 2 Level Approvers
book
Article ID: 145407
calendar_today
Updated On:
Products
Clarity PPM SaaSClarity PPM On Premise
Issue/Introduction
We require timesheets to be approved by Project manager first and then by Resource manager.
If this is not possible, instead of Resource manager, is there a way to configure Project manager as the approver?
Environment
Release : All Supported Releases
Resolution
Project Manager Approval is the one process available out of the box that would achieve the requirement of going to the project manager instead of resource manager
This process is not available by default, it has to be activated and validated to be used.
2. There's no process available out of the box that goes to both resource manager and project manager, but you could create a custom process to give the results desired
The Project Manager Approval process could be used as a foundation of how to get started in creating this additional custom process
See more information on processes including how to create a process at: Configure Processes
Note: There is also another timesheet process available that is: Conditional Automatic Approval, more details referenced in the above link.